Third-party measurement and verification of over 100 sites per year to ensure all measures and project requirements for the annual inspection period have been delivered and met. Sites including but not limited to the following:
Irvine Company – 501 W. Broadway:
High efficiency fan wall retrofit with VFDs
Chilled water control retrofit
Hologic – GCD-1:
High efficiency chiller retrofit with VFDs
Chilled and condenser water control retrofit
Althea:
High efficiency chiller retrofit with VFDs
AHU supply fan VFD addition
San Diego Police Department:
High efficiency chiller retrofit with VFDs
Chilled water control retrofit
City of El Cajon:
High efficiency chiller retrofit with VFDs
High efficiency supply fans retrofit with VFDs
Chilled water control retrofit
Irvine Company – Symphony Towers:
High efficiency fan wall motors with VFDs
High efficiency chilled water motors with VFDs
Chilled water control retrofit
ATT:
High efficiency chiller retrofit with VFDs
Chilled water control retrofit
Sekisui Diagnostics:
High efficiency supply fans retrofit with VFDs
Constant volume to variable volume air side control retrofit